Rapid fast-setting repair mix
Designed for urgent repairs (filling cracks, potholes, voids, etc.) of horizontal and vertical concrete, cement-sand mortar and monolithic screed substrates, as well as anhydrite and asphalt-concrete substrates.
Technical data
| Composition | Cement mix with mineral fillers and organic modifiers |
| Application temperature, °C | +5°C to +30°C. |
| Full cure time | after 60 min. |
| Adhesion (bond strength), MPa | at least 0.8 MPa. |
| Shelf life from date of manufacture | 12 months from the production date indicated on the packaging. |
| Compressive strength limit, MPa, not less than | • flexural strength: at least 5 MPa; • compressive strength: at least 20 MPa. |
| Mix use | 1.5 kg/m² per 1 mm of layer thickness. |
| Storage | In the manufacturer's sealed original packaging, in dry rooms on wooden pallets, 12 months from the production date indicated on the packaging. |
| Packaging | Bag, 25 kg. |
| Disposal | Dispose of product residue as construction waste, and packaging as household waste. |
Application
Preparing the mortar: pour water (temperature +15°C to +20°C) into a clean container at a ratio of:
- 4 L for filling voids, potholes and cracks, including on vertical surfaces, when repairing steps, stairwells, etc.;
- 4.5-5.0 L for filling.
Mix the resulting mortar with a low-speed mixer until a smooth, lump-free mass is obtained. Let the mortar rest for about 5 minutes, then stir again. Excess water when preparing the mortar reduces its mechanical strength and causes it to separate. The prepared mix must be used within 10 minutes of preparation.
Fill surface defects (voids, potholes, cracks, etc.) with the repair mix and smooth with a trowel. 60 minutes after finishing repair work, the following coatings can be applied to the repaired surface: self-levelling compounds, levelling fillers, etc. If subsequent layers are applied after a longer interval, it is recommended to prime the surface with Kirchland Primer Pro.
24 hours after finishing repair work, the moisture content of hardened Kirchland Rapid mortar does not exceed 3%, and finish floor coverings can be installed. For underfloor heating floors, the mortar temperature should match the substrate temperature (about +18°C). Underfloor heating can be switched on at working power 72 hours after laying the self-levelling compound. If work is interrupted for more than 15 minutes, tools must be washed with water. Hardened mortar can only be removed mechanically.